Environmental Risk Register
600.00
As per
requirement
Post Impact Assessment Study
300.00
As per
requirement
Environmental Evaluation Study
300.00
As per
requirement
Permit to Operate
1,250.00
As per
requirement
Laborator
y
Annual Laboratory Accreditation
500.00
Yearly
Verification of Oilfield Chemicals/Remediation
Products
250.00
3 years
Annual Laboratory QA/QC- Reference material
& Proficiency testing
500.00
Yearly
Approval to produce culture test organisms for
BioMonitoring
500.00
As per
requirement
Environme
nt
General
Post Clean-Up Certificate
250.00
As per
requirement
Certificate of Sampling (Quarterly Effluent and
Groundwater monitoring)
350.00
As per
requirement
Special Studies, Biological Monitoring Studies
200.00
As per
requirement
Measurement Reporting and Verification of
GHG Emmissions
200.00
As per
requirement
Post Remedial Action Plan
100.00
As per
requirement
Emergency Response Plan, JMP Approval for
Alternative crude Evacuation
250.00
As per
requirement
Decommissiong Plan
300.00
As per
requirement
Produced Formation Water disposal permit
400.00
As per
requirement
Hydrocar
bon
Processin
g Plant
and
Installatio
ns
(Refinery/
LNG/GTL)
Environmental Management Plan
300.00 As per
requirement
Point Source Registration (per Facility or
installation)
400.00 As per
requirement
Project Concept Screening Report/Preliminary
Environmental Risk Assessment
250.00 As per
requirement
Environmental Risk Register
500.00 As per
requirement
Post Impact Assessment Study
400.00 As per
requirement
RegulationsPDF9