Library / DPR GUIDELINES FOR APPROVAL TO CONSTRUCT AND OPERATE PETROLEUM PRODUCTS FILLING STATION Procedure and conditions for granting approval for the construction and operation of Petrol Station; these guide
DPR GUIDELINES FOR APPROVAL TO CONSTRUCT AND OPERATE PETROLEUM PRODUCTS FILLING STATION Procedure and conditions for granting approval for the construction and operation of Petrol Station; these guide
Page 3 of 8
REQUIREMENTS FOR ISSUANCE OF STORAGE AND SALES
LICENCE
The following conditions must be met before storage and sales licence can be granted.
(i)
A minimum of three (3) underground storage tanks (one each for PMS,
DPK, and AGO.)
(ii)
A minimum of three (3) dispensing pumps(one each for PMS,DPK and
AGO)
(iii)
Office building: Two (2) offices, sales room, toilet, lube bay/store
(Optional).
(iv)
Well concreted forecourt “IN/OUT” drive way inclusive.
(v)
Wall fence demarcating the station (minimum height of 1.5m high).
(vi)
Good drainage Network.
(vii)
Safety facilities (Fire Extinguishers, Sand Buckets, strategic display of
“NO SMOKING” warning signs.
(viii)
Station Sign post/logo of company/outlet.
(ix)
Standard canopy over PMS pumps (mandatory) with company name and
logo boldly written.
(x)
Standby Generator.
(xi)
Accessible Potable water source.
(xii)
Standard (51” x 30”) price bill board with changeable price mechanism
DOCUMENTS REQUIRED
(a)
Products U/G tanks pressure test report/Certificate and Leak
detection test (original printout).
(b)
Photographs of the station 8” X 10” (not computer generated
photographs
(snapped from different angles such that
in/out
driveways pumps and other facilities are clearly
shown).
(c)
Current Fire certificate.
(d)
Application form with Bank draft attached (amount depends on
storage
capacity).
(e)
Evidence of trained attendants.
(f)
Application letter addressed to:
The Operations Controller,
RegulationsPDF3