Library / GAS EXPLORATION AND DEVELOPMENT – PERMITING PROCEDURES & REQUIREMENTS PERMIT REQUIREMENTS Gas Field

GAS EXPLORATION AND DEVELOPMENT – PERMITING PROCEDURES & REQUIREMENTS PERMIT REQUIREMENTS Gas Field

Page 3 of 3

Open the PDF at page 3

7.  
The following related drilling operations shall also be conducted with prior approval:  
1. Well plug back & abandonment 
2. Well side track 
3. Well deepening 
4. Well change of target 
5. Well re-entry after temporary suspension of activities 
6. Casing recovery from a well. 
7. Zone switch. 
8. 
TEMPORARY 
GAS FLARING 
PERMIT/ 
WAIVER 
The permit for gas flaring waiver application should contain the 
following: 
1. Name of field and facility where flaring is expected. 
2. The reason and justification for the temporary gas flaring exercise. 
3. Actions/processes already put in place to reduce the flare volumes 
before seeking the permit/waiver. 
4. The duration over which gas will be flared and total volume of gas 
expected to be flared. 
5. Any other information/supporting facts to justify the application for 
flare permit/waiver.