Library / [Type text] May 2017 GENERAL REQUIREMENTS AND GUIDANCE INFORMATION FOR THE ESTABLISHMENT OF
[Type text] May 2017 GENERAL REQUIREMENTS AND GUIDANCE INFORMATION FOR THE ESTABLISHMENT OF
Page 6 of 6
Page 5 of 5
15. Applicable Fees for Participation
This is as prescribed and stipulated by DPR in the published Guidelines as given below
License to Establish (LTE)
Statutory
DPR Processing Fee
USD 50,000.00
N500,000.00
Authority to Construct (ATC)
DPR processing fees
N500,000.00
License to Operate (LTO)
Statutory
DPR processing fees
USD 1,000/1000 BPD up to 30,000BPD
USD 100,000.00 for 30,000 BPD & Above
N500,000.00
16. Calendar of Activities for Modular Refinery Establishment
Under the modular refineries initiative, a timeline of key activities to enable smooth and speedy
completion of the process for selection is outlined below
S/N
ACTIVITY
DATE
REMARK
1
WORKSHOP:
-
Organized
for
interested Companies/Investors in
Modular Refinery Establishment
To
Be
Advised
Objective to educate companies/ investor
on
expectations,
the
processes
and
conditions to set up modular refineries.
2
SUBMISSION OF APPLICATIONS: -
Applications
forms
and
the
Guidelines
2 – 3 months
after
workshop
Interested
companies/investor
submits
applications and requirements for LTE as
listed in the Guidelines.
3
TECHNICAL
EVALUATION:
-
Evaluate applications and submit
report by date
1
month
after
submission
Objective to analyze and weigh the
technical capacities and capabilities of
the companies.
4
PUBLISH REPORT OF SUCCESSFUL
COMPANIES: - Accept report and
make public
2
weeks
after
evaluation
Only
qualified
technical
submissions
published and deemed to have passed LTE
For more information, please visit the Department of Petroleum Resources Website at
www.dpr.gov.ng to download the following:
i.
Guidelines for the establishment of Hydrocarbon Processing Plants
ii.
Supplementary guidelines for the Design, Construction and Operation of Modular (mini)
Refinery Plants in Nigeria
FEDERAL MINISTRY OF PETROLEUM RESOURCES
OtherPDF20172017-056