15. Applicable Fees for Participation 
This is as prescribed and stipulated by DPR in the published Guidelines as given below 
 
 
 
License to Establish (LTE) 
Statutory   
 
DPR Processing Fee 
 
USD 50,000.00  
 
N500,000.00 
Authority to Construct (ATC) 
DPR processing fees          
 
N500,000.00 
License to Operate (LTO) 
Statutory 
 
 
DPR processing fees          
 
USD 1,000/1000 BPD up to 30,000BPD  
USD 100,000.00 for 30,000 BPD & Above 
 
N500,000.00 
 
16. Calendar of Activities for Modular Refinery Establishment 
Under the modular refineries initiative, a timeline of key activities to enable smooth and speedy 
completion of the process for selection is outlined below 
 
S/N 
ACTIVITY 
DATE 
REMARK 
1 
WORKSHOP: 
- 
Organized 
for 
interested Companies/Investors in 
Modular Refinery Establishment 
To 
Be 
Advised  
Objective to educate companies/ investor 
on 
expectations, 
the 
processes 
and 
conditions to set up modular refineries. 
2 
SUBMISSION OF APPLICATIONS: - 
Applications 
forms 
and 
the 
Guidelines 
2 – 3 months 
after 
workshop 
Interested 
companies/investor 
submits 
applications and requirements for LTE as 
listed in the Guidelines.  
3 
TECHNICAL 
EVALUATION: 
- 
Evaluate applications and submit 
report by date 
1 
month 
after 
submission  
Objective to analyze and weigh the 
technical capacities and capabilities of 
the companies. 
4 
PUBLISH REPORT OF SUCCESSFUL 
COMPANIES: - Accept report and 
make public 
2 
weeks 
after 
evaluation  
Only 
qualified 
technical 
submissions 
published and deemed to have passed LTE 
 
For more information, please visit the Department of Petroleum Resources Website at 
www.dpr.gov.ng to download the following: 
 
i. 
Guidelines for the establishment of Hydrocarbon Processing Plants 
ii. 
Supplementary guidelines for the Design, Construction and Operation of Modular (mini) 
Refinery Plants in Nigeria 
 
 
FEDERAL MINISTRY OF PETROLEUM RESOURCES