Applicable to all Oil & Gas Operators  
GUIDELINES FOR THE ESTABLISHMENT AND OPERATIONS OF CNG 
COMPRESSION FACILITIES IN NIGERIA 
Code: DPR Guide 0029 - 2020 
 
Revision  Date: 1st September 2020 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
7 
xv. 
Well-stocked First Aid Box 
xvi. 
Adequate Fire Water Storage, Fire Hydrant system/control points and booster 
pumps 
 
2.5.1 
Renewal of License to Operate 
On the expiration of an existing LTO for a facility, the company shall apply through their 
profile on the appropriate portal, for the renewal of LTO. The company shall pay the 
applicable fee and upload current and valid documents used for the LTO application. DPR 
officers will conduct an inspection of the facility and ancillary equipment. The inspection 
shall confirm, at the minimum, the status and integrity of all equipment and amenities in 
line with relevant standards. 
2.6 
Relocation of Existing Facility 
If a company desires to relocate an existing and licensed facility to a new site, the applicant 
must submit the justification (reasons) for the proposed relocation of the facility. The 
conditions for the grant of Approval to Construct and LTO for a new Facility shall be the 
same for relocated Facility.  
2.7 
Lease/Takeover of CNG Compression Facility  
The company for Lease/Takeover of a Site Suitability Approval (SSA), ATC and LTO shall pay 
the prescribed application fee and submit the following documents.   
a. Duly signed Sales Agreement by both parties.  
b. Letter of Release.  
The requirements as applicable for SSA, ATC and LTO shall apply. Inspection may be carried 
out as part of the process.