GUIDELINES FOR THE ESTABLISHMENT AND OPERATIONS OF CNG 
COMPRESSION FACILITIES IN NIGERIA 
Code: DPR Guide 0029 - 2020 
 
Revision  Date: 1st September 2020 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
9 
tanks, fittings, pumps, manifolds, meters, hoses, valves, and other equipment and 
accessories of the facility shall be designed for efficient and safe operations in line with 
applicable codes and standards. The installation and commissioning of the system shall 
only be undertaken by competent persons and companies, in accordance with 
manufacturer's instructions and best practices. Written Standard Procedures shall be 
drawn up and used for installation and/or commissioning. Further conditions governing 
the establishment of a Compression Facility are as follows:   
i. 
Participation of DPR representatives in the project and mandatory witnessing of 
milestone construction activities such as tank burial, pressure/leak test of the 
tanks and tank calibrations.  
ii. 
All critical equipment and piping shall be commissioned after installation in 
accordance with manufacturer’s instructions. Integrity tests and other applicable 
tests shall be conducted companies with relevant OGISP permits and witnessed 
by the Department.   
3.2 
Facility Layout & Site Selection  
3.2.1 
Site Selection Criteria 
Any site chosen for the facility shall be sufficiently spacious to allow it to be designed 
to minimize the risks from CNG as applicable to any structure close to the facility and 
person likely to be at or near the facility.  Furthermore, the site shall meet the 
following requirements:   
i. 
The size of the proposed land site shall be adequate and accessible from the 
roadside. 
ii. 
The site shall not be within, under or close to know hazards such as pipeline Right 
of Way (ROW), high voltage cable, railways etc. 
iii. 
The minimum horizontal distance between the shell of a pressurized tanks and 
the line of adjoining property that may be developed shall be as shown in Table