Library / GUIDE FOR THE ESTABLISHMENT AND OPERATIONS OF DOWNSTREAM GAS FACILITIES IN NIGERIA (LPG, CNG, LNG) ISSUED BY
GUIDE FOR THE ESTABLISHMENT AND OPERATIONS OF DOWNSTREAM GAS FACILITIES IN NIGERIA (LPG, CNG, LNG) ISSUED BY
Page 87 of 194
Applicable to all Oil & Gas Operators GUIDELINES FOR THE ESTABLISHMENT AND OPERATIONS OF GAS STORAGE AND UTILISATION FACILITIES IN NIGERIA Code: DPR Guide 0020 - 2020 Revision Date: 1st September 2020 This is a property of the Department of Petroleum Resources. All rights reserved i Table of Contents 1 INTRODUCTION ................................................................................................................ 1 1.1 Purpose ....................................................................................................................... 1 1.2 Scope .......................................................................................................................... 1 1.3 Definition of Terms .................................................................................................... 1 2 APPLICATION, APPROVAL AND LICENSE PROCEDURE FOR Facility ............................ 2 2.1 Application Overview ................................................................................................. 2 2.2 Site Suitability Approval (SSA) .................................................................................. 2 2.2.1 Procedure for Site Suitability Inspection ........................................................... 3 2.2.2 Validity of Site Suitability Approval .................................................................... 3 2.3 Approval to Construct/Approval to Install ................................................................ 3 2.3.1 Review of Submitted Documents and Drawings .............................................. 4 2.3.2 Conditions on the Approval to Construct/Install .............................................. 4 2.4 License to Operate (LTO) .......................................................................................... 5 2.5 Procedure for Pre-License Inspection ....................................................................... 6 2.5.1 Pre-License Inspection for New or Renewal of License of Operate ................ 7 2.6 Relocation of Existing Facility .................................................................................... 7 2.7 Lease/Takeover of Facility ......................................................................................... 7 2.8 Modification of Facility .............................................................................................. 8 2.9 Decommissioning of Facility ...................................................................................... 8 3 MINIMUM DESIGN, CONSTRUCTION AND INSTALLATION REQUIREMENTS .............. 8 3.1 General Requirements ............................................................................................... 8
OtherPDF87