Applicable to all Oil & Gas Operators  
GUIDELINES FOR THE OPERATIONS OF PETROLEUM REFINING FACILITIES 
Code: DPR GUIDE 0044 - 2021 
 
Review Date: 3rd February 2021 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
7 
iv. 
Product quality clearance from DPR 
v. 
Evidence of payment of processing fee of N250,000 for every 250,000 litres of 
finished product or part thereof 
 
Approval to Evacuate Intermediate Products  
Application for evacuation of intermediate products shall be on case basis. 
i. 
Product type, and reason for evacuation.  
ii. 
Mode of evacuation (truck, ship, barge, rail etc.) 
iii. 
Provide evidence of DPR approval to use the product in-country. 
iv. 
Plan for DPR to monitor the discharge.  
v. 
Evidence of payment of processing fee of N250,000 for every 250,000 litres of 
intermediate product or part thereof. 
6.2 
EXPORT AND IMPORT PERMIT 
 
Import Permit 
The refiner shall apply for approval to import product into the refining plant via online 
portal and provide the following information: 
a. Relevant Invoices. 
b. Bill of Lading. 
c. Photocopy of Approved Form “M”. 
d. Clearance or Import duty payment from Nigeria Customs & Excise. 
e. Import Clearance Form duly certified by DPR representative at the refinery. 
f. Detail cargo information, such as direct shipment, ship-to-ship, name of mother 
vessel, certificate of quality, last port of call etc. 
g. A copy of the “Certificate of Quantity” and “Certificate of Quality” of previous 
imported and delivered products duly authenticated by DPR (to be made 
available (for renewal of import permit)).