GUIDELINES FOR PRODUCERS ASSOCIATED GAS UTILISATION PROJECTS 
Code: DPR Guide 0008 - 2020 
 
Revision Date: 1st August 2020 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
8 
3. 
Execution of a Connection Agreement with the relevant Producer within sixty 
(60) days of the date of the award of Approved PAFOP Applicant status. 
4. 
If applicable, execution of the Deliver or Pay Agreement with the relevant 
Producer within sixty (60) days of the date of the award of Approved PAFOP 
Applicant status. 
5. 
Upon the execution of the MDA, a Milestone Bond shall be posted. The 
Milestone Bond will be in an amount as prescribed in table 2 of Schedule C of 
the Guidelines for Grant of Permit to Access Flare Gas. 
6. 
Payment of the prescribed Award Fee for Grant of Permit to Access Gas (see 
Schedule B of the Guidelines for Grant of Permit to Access Flare Gas) shall be 
made within sixty (60) days of the date of award of Approved PAFOP 
Applicant status. 
7. 
Notwithstanding the above, the Approved PAFOP Applicant must be a 
Nigerian registered company to be granted a Permit to Access Flare Gas. 
h. 
In the event that an Approved PAFOP Applicant is unable to fulfil the above 
conditions, a revocation notice of the approval shall be issued to the Approved 
PAFOP Applicant by the Department of Petroleum Resources on behalf of the 
Minister. 
i. 
Upon issuance of a revocation notice, where the Approved PAFOP Applicant fails to 
fulfil the conditions as stipulated in Section 4.1 (g) of these Guidelines within thirty 
(30) days, the Approved PAFOP Applicant status shall be deemed forfeited.  
j. 
If all the conditions in Section 4.1 (g) are met, then an Approved PAFOP Applicant 
shall be awarded a Permit to Access Flare Gas and become a Permit Holder pursuant 
to the Regulations.  
k. 
All Producers’ Approved Flare Out Projects must meet all Applicable Standards