GUIDELINES FOR THE DESIGN, CONSTRUCTION, OPERATION AND 
MAINTENANCE OF OIL AND GAS PIPELINE SYSTEMS IN NIGERIA  
Code: DPR Guide 0027 – 2021 
 
Effective Date: 14th October 2021 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
8 
An application for re-validation shall be accompanied by a payment of N 250,000:00 only, 
made payable to the Department of Petroleum Resources as processing fees. 
2.4.2 Pipeline Community Engagement  
Every pipeline development activity shall be expected to develop a sustainable Community 
Engagement Program (CEP) for all its pipeline communities. The CEP shall optimally 
involve all necessary stakeholders in both its generation and implementation and shall be 
submitted for the approval of the Department along with the request for grant of Oil 
Pipeline Licence.  As part of the community engagement program, company shall consider 
incorporating the following: 
i. 
Pipeline community shall supply manpower required for conducting an effective 
R.O.W surveillance coordinated by the community head. Surveillance activity 
shall be conducted under an MOU executed between the pipeline owner and the 
community leader spelling out responsibilities, allowances and reporting pattern. 
ii. 
Pipeline owner shall optimally utilize pipeline community local content capacity 
in executing all pipeline related projects. 
Note: Renewal of OPLL shall be granted only on the submission and approval of a 
comprehensive pipeline CEP.    
2.5 Conceptual Design / Front-End Engineering Design 
All pipeline development shall duly obtain an approval the conceptual design/FEED prior 
to commencement of detailed design and construction. Conceptual Design are 
Engineering design activities required to specify pipeline development programs such as 
SOW, BFD, technical specifications etc. Relevant technical officers of the Department shall 
be nominated to provide regulatory guidance throughout the entire project execution. 
2.5.1 Responsibilities of DPR Project Representatives 
The Relevant technical officers of the Department nominated for the project shall be 
viewed as part and parcel of the Project Management Team, therefore, shall be actively 
involved and abreast of all activities for the delivery of the project.  Their responsibilities 
and deliverables include but not limited to the following:  
i. 
Participation in the development of project deliverable as applicable.  Review, 
scrutinize and monitor the various elements of project phases and related work