Applicable to all Oil & Gas Operators  
GUIDELINES FOR THE DESIGN, CONSTRUCTION, OPERATION AND 
MAINTENANCE OF OIL AND GAS PIPELINE SYSTEMS IN NIGERIA  
Code: DPR Guide 0027 – 2021 
 
Effective Date: 14th October 2021 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
ii 
2.6.4 
Summary of Environmental Studies ................................................................... 13 
2.7 
Notification for Construction .................................................................................. 13 
2.7.1 
Factory Acceptance Tests & Pipeline Mill Inspections ....................................... 14 
2.8 
Pre-Commissioning .................................................................................................. 14 
2.9 
Commissioning / Introduction of Hydrocarbon ...................................................... 14 
2.10 
Licence To Operate Pipelines .................................................................................. 15 
2.11 
Transfer of Ownership ............................................................................................. 16 
2.11.1 
Application for Transfer of PTS ......................................................................... 16 
2.11.2 
Application for Transfer of OPLL ....................................................................... 16 
3. LIQUID PETROLEUM TRANSPORTATION PIPING SYSTEMS ............................................. 17 
3.1 
Definition ...................................................................................................................17 
3.2 
Minimum Design Criteria ..........................................................................................17 
3.3 
Minimum Construction Requirements.................................................................... 18 
3.3.1 
Minimum Requirements for Pipeline Burial ....................................................... 19 
3.4 
Procedure For Inspection and Testing. .................................................................... 21 
3.4.1 
Guide to Pipeline Testing ................................................................................... 22 
3.5 
Corrosion Control ..................................................................................................... 22 
3.5.1 
External Corrosion Control of Buried or Submerged Pipeline ........................... 23 
3.5.2 
Internal Corrosion Control ................................................................................. 24 
4. GAS TRANSMISSION AND DISTRIBUTION PIPELINE ........................................................ 24 
4.1 
General Design Considerations ............................................................................... 24 
4.2 
Design Criteria and Materials Specifications .......................................................... 24 
4.2.1 
Design and Construction of Gas Pipeline ........................................................... 25 
4.2.2 
Requirements for Inspection and Testing of Gas Pipelines ............................... 26 
4.3 
Gas Pipelines Made with Materials Other Than Ductile Steel ............................... 27 
4.3.1 
Cast Iron Materials: ............................................................................................ 27 
4.3.2 
Plastic Materials ................................................................................................. 27 
5. FLOWLINE, PIPELINE & RISER SYSTEMS FOR OFFSHORE OPERATIONS ....................... 29 
5.1 
Basic Statutory Approvals ....................................................................................... 29