Afrindustria/ Gas Gap Monitor

Library / GUIDELINES FOR THE ESTABLISHMENT OF A NATURAL GAS PLANT FACILITY IN NIGERIA. DPR 2006

GUIDELINES FOR THE ESTABLISHMENT OF A NATURAL GAS PLANT FACILITY IN NIGERIA. DPR 2006

Page 11 of 13

Open the PDF at page 11

 
11 
q) 
A SAFE Chart analysis of the plant. 
r) 
An Environmental Impact Report of the plant 
s) 
Flow assurance report 
t) 
Any other requirement as the Director may specify from time to time.  
 
On application to relocate gas plant facilities, the statutory non-refundable application 
fee for Licence to establish a gas plant facility shall apply. 
 
Upon receipt and completion of the review of the above, the Director shall appoint 
experts to carry out a physical inspection of the plant and accessories on location in 
order to verify the integrity of the plant elements. If satisfied, the Director may grant an 
approval for the plant to be relocated to Nigeria, at the total risk of the promoters. 
 
The licence to construct a gas plant facility and the licence to operate gas plant facility 
shall apply at the appropriate phase of development of the project. 
 
 
 
 
Department of Petroleum Resources