Library / GUIDELINES FOR THE ESTABLISHMENT OF A NATURAL GAS PLANT FACILITY IN NIGERIA. DPR 2006
GUIDELINES FOR THE ESTABLISHMENT OF A NATURAL GAS PLANT FACILITY IN NIGERIA. DPR 2006
Page 11 of 13
11 q) A SAFE Chart analysis of the plant. r) An Environmental Impact Report of the plant s) Flow assurance report t) Any other requirement as the Director may specify from time to time. On application to relocate gas plant facilities, the statutory non-refundable application fee for Licence to establish a gas plant facility shall apply. Upon receipt and completion of the review of the above, the Director shall appoint experts to carry out a physical inspection of the plant and accessories on location in order to verify the integrity of the plant elements. If satisfied, the Director may grant an approval for the plant to be relocated to Nigeria, at the total risk of the promoters. The licence to construct a gas plant facility and the licence to operate gas plant facility shall apply at the appropriate phase of development of the project. Department of Petroleum Resources
GuidelinesPDF11