Afrindustria/ Gas Gap Monitor

Library / GUIDELINES FOR THE ESTABLISHMENT OF A NATURAL GAS PLANT FACILITY IN NIGERIA. DPR 2006

GUIDELINES FOR THE ESTABLISHMENT OF A NATURAL GAS PLANT FACILITY IN NIGERIA. DPR 2006

Page 9 of 13

Open the PDF at page 9

 
9
SECTION 3 
 
3.0 
LICENSE TO OPERATE GAS PLANT FACILTY 
 
3.1 
COMMISSIONING AND OPERATING LICENCE 
 
Upon mechanical completion of the plant, a pre-commissioning inspection of the 
facility shall be carried out by the Department prior to the issuance of operating licence. 
 
The following shall be the pre-requisites to quality: 
 
1) 
A qualified gas manager is appointed and his appointment is notified in writing 
to the Director of Petroleum Resources. 
2) 
Complete equipment reports on all critical equipment such as pressure vessels, 
heat exchangers, fractionation column, compressors, drivers, rotating equipment 
and storage tanks. 
3) 
Completion of all metering equipment and systems to approved standards. 
4) 
Availability of adequate spare parts, chemicals, catalysts, lubes, greases and 
other operating consumable materials in the warehouse appropriately codified 
and organized. 
5) 
Availability of commissioning spare parts, apart from operating spare parts, all 
properly coded and arranged in the warehouse. 
6) 
Approved operating manuals, maintenance manuals, mechanical catalogues, 
would have all been supplied, subject to appropriate modifications after 
commissioning. 
7) 
Approved operating and maintenance organization and availability of trained 
manpower in sufficient strength. 
8) 
Functional and effective fire prevention and fighting organization already in 
existence. 
9) 
Functional and effective Safety enforcement Organization and Policies already 
in existence. 
10) 
All approved engineering drawings in agreed numbers of copies have been 
supplied by the contractor, subject to modifications to reflect changes during 
construction. 
11) 
The quality control laboratory is completed and functional. 
12) 
A well-staffed and equipped First Aid Clinic is in place. 
13) 
All other provisions, which are reasonably required to facilitate effective 
commissioning of the plant, have been made. 
14) 
Confirmation that all-environmental protection standards during design have 
been met. 
15) 
Payment of prescribed license fees. 
 
 
3.2 
PLANT OPERATION 
 
a) 
The gas plant facility shall be operated in compliance with the provisions of the 
Petroleum Refining Regulations, 1974 and any regulations that may come in 
force.