Applicable to all Oil & Gas Operators  
GUIDELINES FOR THE IMPLEMENTATION OF RISK BASED INSPECTION IN 
THE NIGERIAN OIL AND GAS INDUSTRY 
Code: DPR Guide 0022 - 2020 
 
Revision Date: 1st August 2020 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
5 
vi. 
Equipment/Devices 
inspection 
strategies 
and 
methodologies 
(including 
Management   of   Change, Deviations   and   Non-conformances   resolution 
procedures). 
vii. 
RBI documentation procedure. 
3.3 
RBI Methodology Demonstration  
A workshop shall be arranged with the DPR to evaluate the submission and to offer an 
opportunity for the Operator to demonstrate the capacity to deploy the RBI approach in 
line with   the   intent   of   the   applicable   legislation(s) and   international   best 
practices/standards and sustain its implementation. The RBI methodology and processes 
shall conform to and meet the minimum expectations set forth by the current versions of 
American Petroleum Institute (API) Recommended Practice (RP) - API RP 580, API RP 581 
and/or any other relevant internationally recognised systems and processes for RBI.  To 
apply RBI on equipment/device(s) in existing facilities/assets, an Operator would in 
addition, be required to demonstrate compliance with the prescriptive inspection and 
maintenance regime being implemented to the satisfaction of the Department. Also, the 
Operator shall ensure that the Department’s representative(s) are duly familiar with all the 
processes and software to be deployed. The review of the submission and the outcome of 
the workshop, if found satisfactory, shall form the basis for issuing an approval-in-principle 
to an Operator for the implementation of an RBI approach.  
The decision for a submission on RBI methodology to be approved or otherwise will largely 
depend on the description of risk analysis to be carried out or updated during the RBI 
phases and cycle or to which the consent/approval is applicable. Also, the factors 
contributing to final risk assessment which include but not limited to the following are 
considered: - 
i. Team members performing the assessments and their qualifications  
ii. Reassessment interval