Midstream and Downstream Decommissioning and Abandonment Regulations Under Section 232 and 233 of the Petroleum Industry Act (2021). DRAFT DATE: 10/06/2022
Page 5 of 13
l. schedule, indicating details of the decommissioning and abandonment time scale for the proposed option, including a schedule showing the dates at which the various stages of the decommissioning and abandonment are expected to start and finish. m details of the arrangements by which the licencee will keep the Authority informed of the progress of decommissioning and abandonment. n. a description of the post-decommissioning and abandonment monitoring and maintenance phase, including steps to be taken to ensure maintenance and safety, where any installation, structure or pipeline remained disused and in position or are to be partly removed. (3)(i) In respect of the decommissioning and abandonment of any pipelines, storage tanks, petroleum products tank farms and jetties, processing or other facilities or infrastructure relating to a licence for midstream and downstream petroleum operations offshore, the licencee shall make an application to the Authority for approval to decommission and abandon at least thirty-six (36) months prior to the proposed start date of the decommissioning and abandonment programme. (b)(ii) An application under Regulation 13 (3)(i) of these Regulations shall be accompanied by a decommissioning and abandonment programme in a form prescribed by the Authority in addition to the requirement in Regulation 11 (a) which shall comprise of – a. Description of items to be decommissioned and abandoned, inclusive of diagrams, covering – (i) Support structures for offshore fixed and floating installations at the time of removal (type, size, arrangement and weights). (ii) Topsides for offshore fixed and floating installations (type, size, configuration, equipment and weights). (iii) Subsea equipment and installations on or in the seabed (size, weight, height above seabed, whether piled or not, type of construction and material, details of interaction between equipment and other uses of the sea, such as fishing). (iv) For pipelines, flow lines and umbilicals – lengths, diameters, type of construction, the extent of burial, trenching and details of any concrete mattresses, frond mattresses, grout bags, rock-dump or other materials used to cover the lines. (v) Details of any subsea facilities that form part of the pipelines, such as production line end manifold, umbilical termination assembly, riser anchor bases). (vi) Information about the stability of the pipelines including details of any spanning or exposure (Met-ocean data, survey data and history to support information given in this section should be included as an annex to the programme, live pipeline survey information may be relevant). (vii) Details of interaction between any part of the pipelines and other uses of the sea (such as fishing activity, both historical and depending on the field may be necessary to estimate future activity).
RegulationsPDF5