Midstream and Downstream Decommissioning and Abandonment Regulations Under Section 232 and 233 of the Petroleum Industry Act (2021). DRAFT DATE: 10/06/2022

Page 7 of 13

Open the PDF at page 7

(e)  
any removal or partial removal of an installation, structure or transportation 
pipeline is to be performed in a manner that guarantees sustainable 
environmental development;  
 
(f)  
any recommendation to leave an installation, structure or gathering line in place 
is made with regard to its likely deterioration and to the present, possible and 
future effects on the environment and in the case of offshore installations and 
structures, consistent with the applicable good international petroleum industry 
practices; 
 
(g)  
relevant environmental, technical, and commercial regulations or standards are 
complied with. 
 
 
(2) Where the Authority declines to approve the decommissioning and abandonment 
programme, it shall notify the licencee of its decision in writing stating the reasons for the 
refusal.   
 
(3) Where the Authority fails to notify the licencee of its decision on the application within one 
hundred and eighty (180) days from the date of submission of the application as prescribed 
in this Regulation, the application shall be deemed approved. 
 
 
Rejection of an Application for a Decommissioning and Abandonment Programme  
 
15. (1) An application for a decommissioning and abandonment programme pursuant to these 
Regulations may be rejected by the Authority where it does not meet the requirements 
provided that the licencee shall be given an opportunity to submit an amended or modified 
application within a reasonable time. 
 
(2) Where the licencee fails to submit an amended or modified application within the time 
specified or submits an amended or modified application which is not in compliance with 
approved decommissioning and abandonment plan, the Authority shall refuse to approve the 
application and notify the licencee of its decision in writing.  
 
(3) where the Authority refuses an approval under the circumstances of Regulation 15(2), the 
Authority shall have such decommissioning and abandonment program carried out by a third 
party to be financed from the decommissioning and abandonment fund pursuant to section 
233 (3) of the Act. 
 
Requirement for Public Consultation 
 
16. (1) Prior to the submission of an application for any decommissioning and abandonment 
programme as provided for in these regulations, a licencee shall conduct public consultations 
with stakeholders, including communities affected by the activities, public authorities and 
bodies and other interested parties with respect to planned decommissioning and 
abandonment program.  
 
(2)  A licencee shall, in carrying out the consultations under these Regulations — 
 
(a)  
Announce its decommissioning and abandonment programme by placing a 
public notice in One (1) national newspaper and One (1) local newspaper with 
wide coverage and on its publicly accessible website. The notice shall indicate 
where copies of the decommissioning and abandonment programme can be 
viewed, to whom representations should be submitted, and the dates and place 
of public consultations;