2.—(1) The payment to NNPC Limited of the 30% on profit oil and
profit gas revenues due to the Federation for the management of Production
Sharing, Profit Sharing, and Risk Service Contracts is suspended with
immediate effect.
(2) NNPC Limited shall henceforth transfer all profit oil and profit gas
revenues it received as concessionaire/government representative in production
sharing, profit sharing and risk service contracts, to the Federation Account.
(3) All operators/contractors of oil and gas assets held under production
sharing contract shall, from the date of this Order, pay over the Royalty Oil,
Tax Oil, Profit Oil, and Profit Gas and any other interest howsoever described
which is due to the Government of the Federation directly and engross to the
Federation Account.
3.{1) The Commission shall from the date of this Order, pay the
proceeds from all penalties imposed on operators for flaring gas, into the
Federation Account and cease payment of such proceeds into the Midstream
and Downstream Gas Infrastructure Fund (MDGIF).
(2) All expenditure from the MDGIF shall be conducted in line with
extant public procurement laws, policies and regulations.
4.(1)
The Commission shall serve as the interface with licensees
and lessees in respect of integrated operations where upstream and midstream
petroleum operations are fully combined.
(2) The Commission and the Authority shall within two weeks of the
coming into force of this Order, constitute a Joint Project Team responsible
for technical regulation of integrated operations.
(3) The Joint Project Team shall —
(a) develop guidelines for the operation of integrated facilities;
(b)
identify the appropriate licences, permits and fees applicable to
each activity;
(c)
facilitate information and data sharing to ensure a harmonised
regulatory treatment of the integrated facility; and
(d) propose an appropriate framework for the allocation of regulatory
fees between the Commission and Authority, based on the classification of
activities and the agreed regulatory framework.
B 1015
Suspension
of the
payment
of 30%
management
fee on profit
oil and profit
gas revenues
to NNPC
Limited
Suspension
of the
payment
of the Gas
Flare
Penalty
into the
Midstream
and
Downstream
Gas
Infrastructure
Fund
Constitution
ofa Joint
Project Team
to execute
integrated
petroleum
Operations
RegulationsPDF20262026-025