PROCEDURE GUIDE FOR THE GRANT OF PERMIT/APPROVAL/LICENSE FOR 
LUBE OIL BLENDING/WASTE OIL RECYCLING PLANT 
Code: DPR Guide 0021 - 2020 
 
Revision Date: 2nd October 2020 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
2 
product evacuation plan, preliminary safety and environmental impact statement, and 
organizational plans. The following submissions shall be made to the Department of 
Petroleum Resources via LOBP portal www.lobp.dpr.gov.ng: 
i. 
Preliminary marketing plan, indicating whether domestic, export, or if both 
markets are being targeted 
ii. 
Proposed Lube oil blending plant site(s) and proof of acquisition 
iii. 
Infrastructural support strategy 
iv. 
Preliminary organization plan, including staff training plans  
v. 
Financial plan 
vi. 
Payment of DPR processing fees of Two Hundred and Fifty thousand Naira 
(N250,000.00) Only, payable via DPR online payment platform  
vii. 
Plot plan 
viii. 
Block flow scheme showing process configurations and capacities, including 
utilities. 
ix. 
Preliminary base oil acquisition or stocking plan 
x. 
Proposed safety provisions and preliminary environmental impact assessment. 
A satisfactory in-house review of the above submissions by the DPR shall be 
communicated with clearance to proceed into PTE milestone. DPR project engineers shall 
also be attached to monitor the project development from this point forward, at source, 
to facilitate statutory compliance and approval processes. 
2.3 
Approval to Construct 
This approval gate highlights the requisite technical documentations required to 
progress the project to the construction stage. Application for ATC shall be made via 
LOBP portal www.lobp.dpr.gov.ng with the following requirements: 
i. 
A copy of PTE earlier granted to the Company. 
ii. 
Evidence of Payment of ATC Processing fee of Two Hundred and Fifty