 1.2.4    The design and installation of the lock valve shall be approved and supervised by the 
Department of Petroleum Resources. After the installation of the lock valve has been found 
satisfactory by the Director of Petroleum Resources, all the keys to the lock shall be kept in 
the custody of the Department of Petroleum Resources Official – In – Charge of operations 
at the facility. 
1.3 CLASSES OF MEASUREMENTS. 
1.3.1 CLASS A MEASUREMENT  
The metering stations used for the delivery of petroleum to offshore customers and where 
sales contracts are applicable. The DPR officer(s) shall monitor and supervise the systems 
operations as applicable in the terminals for tax or royalty. The required overall 
measurement uncertainty shall be less than 1% on a volume basis for gas or as specified in 
the contract and approved by DPR. 
1.3.2 CLASS B MEASUREMENT 
The metering stations for the delivery of petroleum in commonly used pipeline systems and 
where allocation procedures or joint operating contracts apply. This includes production 
metering for MER allocation. The DPR shall be furnished on a weekly basis the daily 
measurement record of the meter for accountability. The DPR officer(s) physical 
involvement in the system operations shall be intermittent, at least fortnightly. The required 
overall measurement uncertainty shall be less than 1.8% on a volume basis for gas or as 
specified in the contract. 
1.3.3 CLASS C MEASUREMENT 
The metering stations for the delivery of fuel gas within the operator’s operating facility or 
to third party facility. The uncertainty limit shall be ± 2 % of standard volume. The DPR 
involvement is as in CLASS B. 
1.4.4 CLASS D MEASUREMENT 
The Metering station for flare and injection gas measurement. The uncertainty limit shall be 
±5% of standard volume. If the flare gas releases are due to the operational upset, 
blowdown, purging, or ESD operation the meter readings so recorded shall be forwarded 
within 24hours to the DPR nearest office with a detailed report on the scenarios of the 
releases. This report shall form the basis of zero charges on the flare gas releases while 
charges shall be sustained if the flare releases are operational philosophy. The DPR 
officer(s) involvement in the metering operations shall comply with CLASS B measurement 
systems. The uncertainty is given in standard volume, but other units may be requested 
(project specific) e.g. mass energy, etc. 
Note: Any other uncertainty limit may be applicable for fiscal measurement systems if 
validated by a cost-benefit analysis performed and accepted by the DPR.       
1.5 UNCERTAINTY ANALYSIS 
An uncertainty analysis shall be developed for gas metering systems within 95% confidence 
level in accordance with recognized standards. The total gas metering system uncertainty 
shall, for the operating flow range, be below +/- 1.0% (mass metering). If a deviation on any 
of the equipment tolerances exists, it should be demonstrated that the metering system is 