22 
 
 
 
 
 
Applicable to all Oil & Gas Operators  
 
SAFETY CASE GUIDELINES FOR OIL AND GAS FACILITIES IN NIGERIA 
                Code: DPR GUIDE 0036 – 2020 
 
Revision Date: 2nd October 2020 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
6 
SAFETY CASE REVISION 
Safety Case is intended to be a living document, kept up to date and revised as necessary during 
the facility life cycle. Overall, the Operator should ensure that the current Safety Case remains up 
to date and reflects the operational reality of the installation.  
The proponent is required to revise an approved Safety Case and submit for approval, an 
addendum to the Safety Case in the event of any of the following: 
i. 
If there are new developments, modification or changes that alter or introduce Major Accident 
Hazard, affect the safety management system, standards for design or operation or system for 
identifying or evaluating risks of the facility.  
ii. 
If the Operator proposes to carry out activities at the facility that are different from those 
addressed by the Safety Case that is approved. Note: the difference does not have to be 
significant.  
iii. 
If the Operator proposes to decommission or otherwise modify the facility in a way that is not 
already addressed by the Safety Case that is in force;  
iv. 
If a major incident or accident happens and; 
v. 
Any other conditions as may be determined by the DPR. 
In any case, the Operator shall be required to resubmit and obtain approval of a revised Safety 
Case of each facility every five (5) years. The Operator/Facility owner should ensure that such five-
yearly periodic resubmission made to the DPR captures all necessary updates on the facility 
description, safety management system, revalidation of relevant formal safety assessments 
conducted for the facility, incorporation of all changes as a result of any of items 6 (i – v) of these 
Guidelines and any addendum made within the five years period under consideration.