Applicable to all Oil & Gas Operators  
 
SAFETY CASE GUIDELINES FOR OIL AND GAS FACILITIES IN NIGERIA 
                Code: DPR GUIDE 0036 – 2020 
 
Revision Date: 2nd October 2020 
 
 
 
This is a property of the Department of Petroleum Resources. All rights reserved  
 
The purpose of Safety Case can be further described as follows: 
i. 
To ensure that adequate and documented systems are in place to prevent the occurrence 
of major incidents, high potential events and near misses at the facility, and to minimise 
the effects of major incidents that might occur at the facility. The Operator is responsible 
for eliminating the risk of a major incident or, if elimination is not reasonably practicable, 
ensuring that the risk reduction mechanism is followed to minimise the risk to ALARP.  
ii. 
To ensure that the Safety Case draws from safety-related studies and reports related to 
hazard identification, risk assessment, risk control and emergency response planning. 
These will demonstrate that the hazards and risks associated with major incidents are fully 
understood and that control measures in place are adequate, monitored and maintained. 
iii. 
To hold the Operator accountable and review the assumptions on which the Operator’s 
risk minimisation strategy is based. Also, to ensure Operators develop initiatives to further 
reduce the risks identified. Furthermore, periodic reviews and site inspections maybe 
conducted by the DPR to verify that the Operator of a facility meets the objectives and 
standards required in the Safety Case.  
Overall, a well-structured and coherent Safety Case submission will facilitate a proponent’s ability 
to demonstrate to all stakeholders that they have a clear understanding of all credible hazards 
and risks associated with their facility/operation, and that the hazards that could not be eliminated 
are effectively under control. 
3 
TYPES OF SAFETY CASES  
In the Nigerian oil and gas industry, the Safety Cases required by the DPR at different stages in the 
life cycle of facilities are illustrated in figure 3.1. below. The details of submission timeline are 
shown in section 5.2 of these Guidelines.