Library / Page 1 of 67 MIDSTREAM AND DOWNSTREAM PETROLEUM SAFETY AND ENVIRONMENTAL REGULATIONS, 2025
Page 1 of 67 MIDSTREAM AND DOWNSTREAM PETROLEUM SAFETY AND ENVIRONMENTAL REGULATIONS, 2025
Page 35 of 67
Page 35 of 67
(e) retail outlets of combined storage capacity equal to or greater than 270,000 litres
for refined liquid products and greater than 25 metric tons for gas products;
(f) petroleum waste management facilities for the collection, treatment or disposal of
wastes generated from the midstream and downstream petroleum sector; and
(g) any other midstream or downstream petroleum operation which, in the opinion of
the Authority, requires an EMP.
(2) A licensee or permit holder shall submit an EMP under sub-regulation (1) of this regulation,
within six months from the date of the grant of the applicable licence or permit.
59. An EMP submitted by a licensee or permit holder shall be prepared by a person or company
accredited by the Authority in accordance with guidelines issued by the Authority.
EMP to be prepared by
accredited persons.
60. The EMP shall be accompanied with—
(a) a summary of the EIA report from which the plan was derived; and
(b) a report on public consultations between the licensee or permit holder and
stakeholders, on the EIA of the project from which the EMP relates, and the
report shall provide and state the —
(i) evidence of public consultation such as list of attendees and newspaper
publications,
(ii) venue of the consultation where applicable,
(iii) level of stakeholder engagement,
(iv) mode of consultation,
(v) period and method of notice given,
(vi) information on environmental impacts and risks disclosed at the
consultation,
(vii) comments received from stakeholders during consultation and
consideration given to the comments, and
(viii) any other information or document required by the Authority for the review of
the EMP.
(c ) any other information or document required by the Authority for the review of the EMP
Submission of an EMP
61. (1) The Authority shall approve an EMP or a re-submitted EMP in the case of —
(a) an initial submission, within 90 days from date of such submission, and
Approval of EMP