Page | 43 64. (1) The licensee shall, on completion of the construction of the pipeline, give the Authority not less than Fourteen (14) working days written notice of its intention to commence inspection and testing of the pipeline, in the format prescribed by the Authority. (2) Pipeline systems shall be equipped with real time monitoring and Inspection systems. (3) The inspection and test plans (ITPs) including factory acceptance tests (FATs) for line pipes and ancillary equipment i.e., long lead items (LLIs) shall be submitted to the Authority and all functionality test of same shall be witnessed by representatives of the Authority in a manner prescribed in the guideline issued by the Authority. Inspection and testing 65. (1) A licensee shall not commence operation of a pipeline without the prior approval of the Authority; (2) the right of way shall be maintained to provide a clear visibility and give access to the maintenance crew; (3) clear access shall be maintained to valves locations, and ditches shall be protected against washout of the pipeline; (4) the right of way shall be regularly patrolled and inspected for prompt detection of any line break, encroachment or any other situation that may endanger the safety of the pipeline; Operations and maintenance 66. (1) A licensee who desires to upgrade or downgrade the maximum operating pressure of a pipeline or pipeline network shall make an application to the Authority. (2) A licensee shall make an application to the Authority where it desires to change the nature of the fluid transmitted by the pipeline. Pipelines re- rating and change of service 67. (1) A licensee who wishes to discontinue the operation of the pipeline system or its ancillary facilities shall apply to the Authority giving at least three (3) months' written notice of his intention to do so, as prescribed by the Authority. (2) A licensee who desires to resume operations in an abandoned or a discontinued pipeline shall, prior to the resumption of operations, apply to the Authority for approval. Discontinuation, abandonment, and resumption of operation of pipeline System 68. Where a pipeline or pipeline network is to be completely abandoned, such pipeline or pipeline network shall be decommissioned pursuant to the procedures prescribed in Regulations made by the Authority. Decommissioning and abandonment of a pipeline
RegulationsPDF43