Afrindustria/ Gas Gap Monitor

Library / Page | 1 MIDSTREAM AND DOWNSTREAM PETROLEUM OPERATIONS REGULATIONS, 2024

Page | 1 MIDSTREAM AND DOWNSTREAM PETROLEUM OPERATIONS REGULATIONS, 2024

Page 45 of 101

Open the PDF at page 45

 
 
Page | 45 
 
(c) provisions for environmental and social sustainability; and 
(d) payment of prescribed fees. 
 
(3) A licence to establish a terminal or bulk storage facility shall – 
 
(a) specify the provisional deemed coordinates of the terminal or bulk 
storage facility; and 
(b) be valid for 36 months and may be subject to revalidation for a 
further term of 12 months on terms and conditions specified by the 
Authority.  
75. (1) An application to construct a terminal or bulk storage facility shall 
be made in the manner prescribed in guidelines issued by the Authority.  
(2) The Authority may grant a licence to construct a terminal or bulk 
storage facility upon satisfactory evaluation of submissions and payment 
of prescribed fees.  
 
(3) The design, construction, and operation of a terminal or bulk storage 
facility shall be in accordance with the standards and recommended 
practices approved by the Authority. 
 
(4) The design of a terminal and bulk storage facility shall be subjected to 
technical and safety reviews with the participation of  - 
(a) the Authority; and 
(b) third-party moderators for specific safety studies as required. 
(5) All major equipment and critical systems or units shall be subjected to 
integrity inspections, functional tests and integrity tests with the 
participation of the Authority. 
Application 
for licence to 
construct 
76. (1)  An application to operate a terminal or bulk storage facility shall 
be made in the manner prescribed in guidelines issued by the Authority. 
 
(2)   Prior to issuance of licence to operate, every terminal or bulk 
storage facility shall be subjected to — 
 
(a) pre-commissioning and commissioning verification checks; 
(b) physical inspection to ascertain conformity to approved design; 
and 
(c) ascertainment of operating envelope, throughput, and facility 
reliability. 
 
Application 
for licence to 
operate