SCHEDULE 
TABLE OF FEES 
The transferee shall be required to pay theapplicable assignment or transfer 
of licence or permit processing fee in the table below, or five percent (5%) of 
the value of transaction, whichever is higher — 
S/No 
Facility 
Processing Fees 
I. 
| Petrol liquids or gas retail outlets 
500.000 
2 
Depots 
N10.000.000 
3: 
Blending Plants, Waste Recycling 
N3,000.000 
Plants, Bitumen Emulsion Plants, Refilling 
Plants or Thermal Desorption Units 
4. 
| Hydrocarbon 
Processing 
Plant 
USD10,000 for capacities less 
(Refineries, Petrochemicals and Gas 
than |.000BPSD. or less than 
Processing facilities) 
6MMSCFD 
USD 50,000 for capacities 
between 1,000 and 30.000 
BPSD, or between 
6 MMSCFD 
and IS0MMSCFD 
USD 150,000 for capacities 
above 30,000 BPSD, or above 
180 MMSCFD 
5. 
| 
Pipeline 
USD 500 per km 
6. 
| 
Pipeline Distribution Network 
USD 200 per km 
ds 
Pipeline Transportation Network 
USD250 per km 
8 
| Terminals 
USD200.000 
9. 
| CNG Compression Station/Small Scale 
NGN 500,000 
LNG Installations 
Mabe at Abuja this 27th day of February, 2023. 
ENGR. Farouk AHMED 
Authority Chief Executive 
Nigerian Midstream and Downstream Petroleum 