Library / NMDPRA Fact Sheet - January 2026
NMDPRA Fact Sheet - January 2026
Page 3 of 11
Domestic Refineries Performance (January 2026) Update on Refineries Construction WalterSmith (Train 2) ‑ 5,000bpsd Currently undergoing commissioning (January 2026) 61.27% AGO Supply Performance Shut down. However, evacuation of AGO produced while the refinery was operational averaged 0.376 million litres/day. Shut down Shut down Average Capacity Utilization꞉ Average domestic supply January 2026 75 million litres/day Planned domestic supply PMS Supply Performance Actual average domestic supply 40.1 million litres/day 10.9 million litres/day B. t (January 2026) The capacity utilization in January peaked at 67.69%
Fact Sheets & StatisticsPDF20262026-013